Field Name |
State |
Description |
Project Header (Short) |
Display |
The project header provides identifying information for the project and provides a link to the Construction Project Information screen or the Contractor Project page (depending on user). |
Request |
Display |
The number of the request. This number is assigned sequentially by the system.
Note: This field is part of the Subcontractor Approval header fields and provides a link to this screen. This means that if you click the link while on the Subcontractor Approval Request screen, the screen is refreshed. |
Request Status |
Display |
The status of the request.
Requests in Draft status may be modified, deleted, or submitted by the contractor, but may not be viewed or dispositioned by PENNDOT. Requests in Submitted status can be approved or disapproved by PENNDOT users, or can be returned to the contractor in Draft status (Correct button).
Requests that have been approved may be subsequently deleted by PENNDOT users, for example, if the subcontractor fails to perform the work or service, the request must be deleted. Otherwise, PENNDOT must complete a Contractor Evaluation for the firm before the project can be finalized. |
Associated Contractor |
Display |
The business partner name of the prime contractor who submitted the request. |
Associated BPID |
Display |
The business partner ID of the prime contractor who submitted the request. |
Requested Amt |
Display |
The Requested Amount. In draft status, this field displays the sum of the price of all requested items. This field is saved when the request is submitted and does not change based on the approved amount (that is, the approved amount and the requested amount may be different.) |
Business Partner |
Display |
The name of the business partner to whom the prime wishes to subcontract the work or service.
This field provides a link to the Contractor Information (subcontractors only) or Service (services/suppliers) screen for the business partner. |
DBE Cert. |
Display |
The DBE Certification number of the subcontractor. This field is initially displayed as blank. After the request is saved, the screen displays the certification number of the business partner if one exists. If the subcontractor is not certified, the field remains blank after the screen is saved. |
Federal ID |
Display |
The federal identification number (FEIN or FID) of the business partner that is the subject of the request. This field is only displayed for PENNDOT users. |
Minority Code |
Display |
The Minority code associated with the subcontractor. This field is initially displayed as blank. After the request is saved, the screen displays the minority code of the business partner if one exists. If the subcontractor is not certified, the field remains blank after the screen is saved. |
MBE/WBE Commitment |
Display |
This field indicates (Yes or No) whether the subcontractor was submitted on a MBE/WBE Commitment form during the Contract Awards process. If the project is federally funded, the field label changes to “DBE Participation”. |
DBE Participation |
Display |
This field indicates (Yes or No) whether the subcontractor was submitted on a DBE Participation form during the Contract Awards process. If the project is not federally funded, the field label changes to “MBE/WBE Commitment”. |
Business Type |
Selectable |
If the business partner associated with the request appears on more than one DBE Participation or MBE/WBE Commitment form, the prime contractor can select the type of business for which the Subcontractor Approval Request is being submitted. |
Goal Code |
Display |
The type of minority participation goal set for the project. Federally funded projects display “DBE”; while state projects display “MBE/WBE”. |
BEO Function |
Display |
This field displays the business type the business partner is recognized as by the Bureau of Equal Opportunity. If the function is “Supplier”, 60 percent of the value of the approved requested amount is counted toward the Goal Attainment for the project. |
Found on CRP |
Required |
This field allows the authorized PENNDOT reviewer to indicate whether the business partner was found on the list provided by the Contractor Responsibility Program. If this indicator is “Yes”, the request cannot be approved. This field is not displayed in create mode. |
CRP Comments |
Optional |
This field allows the user to enter comments concerning the CRP. This field is not displayed in create mode. |
EDMS Doc Link |
Optional |
This field displays a link to the CRP Check document in the Electronic Document Management System. If no EDMS document exists, the field displays a message to that effect. |
Overseer Subcontractor Information |
Optional |
This field allows the prime contractor to select another subcontractor who will oversee the business partner. The user selects from a filtered list of business partners by clicking the selection arrow to the right of the field. This list only displays business partners who are on approved subcontractor requests for the project and who are not themselves subject to an overseer relationship. |
Business Partner ID |
Display |
The business partner ID of the overseer sub. This field is blank if no overseer exists. |
Approval |
Display |
The number of the approved Subcontractor Approval Request for the overseer. |
Antic. Start |
Required |
This field requires the prime contractor to enter or select the date the subcontractor is anticipated to begin work on the project. |
Antic. Completion |
Required |
This field requires the prime contractor to enter or select the date the subcontractor is anticipated to complete work on the project. |
Subcontracted Amt |
Required |
This field requires the prime contractor to enter the amount they have agreed to pay the subcontractor. This is the amount that is considered for the 50% - Rule calculations. |
Work Complete |
Optional |
This field allows the user to indicate whether the work is complete. |
Minority Pmt Total |
Calculated |
This field displays the total of all minority payments recorded for this subcontractor on this project. The payments themselves are recorded by authorized PENNDOT users on the Minority Payments screen. |
Original Contract |
Display |
The original contract amount. |
Further Subcontracted |
Display |
The sum of the approved amounts from any other approved subcontractor approval requests for the project. |
% Original Contract |
Display |
The percentage of the original contract represented by this subcontractor approval. |
Services Rendered |
Required |
This field requires the prime contractor to select the type of service that the subcontractor, service, or supplier is providing for this request. |
Not Subcontracted |
Display |
The dollar value of the work not subcontracted to others. |
Comments |
Optional |
This field allows the user to enter comments regarding the subcontractor approval request. |
Go Links |
Selectable |
This drop-down list allows the user to select a destination screen to which they want to navigate. This field is used in conjunction with the Go button and performs a function similar to ‘fast pathing’ in a mainframe environment.
Note: The Subcontractor Request Items link takes you to the list of items that have been selected for the request. Initially, the list is displayed with a “no records” message and the user must click the ADD button to begin adding items to the request. |
 |
 |
*****Workflow Status Information***** |
Status |
Protected |
This field displays the status of the request prior to the action taken by the specified user. For example, when the request is saved, this field displays "Draft", and the Name field displays the user name of the person who created the request. |
Name |
Protected |
The name of the person who performed the action listed in the Disposition column. |
Disposition |
Protected |
The disposition of the request performed during this workflow step. For example, Submitted, Approved, Disapproved. |
Date/Time |
Protected |
The date and time the user dispositioned the request. |
Comments |
Editable – Optional |
When the user clicks the solid black triangle to the right of the workflow Status field, the comments that were entered for the corresponding workflow step are displayed on the screen. |