Field Name |
State |
Description |
Project Header |
Display Only |
The full project header fields are displayed as a standard throughout much of ECMS. The header displays general project information including Project number, Short project description, District number, County, Project Status, SR, Section, Municipality, Group and Admin Org Code.
The header also provides quick navigation to other screens related to the same project:
Contractors click the word "Project" to navigate to the Contractor Project page. The words "Project Team" take Contractor users to the Third Party Project Team screen.
PENNDOT, FHWA, Municipal, and Consultant users click the word "Project" to link to the Project Information or Construction Project Information screen (depending on Project Status). The words "Project Team" take these users to the Project Team screen.
The header also provides a 'fast path' to the same screen for a different project number. Users navigate by typing the destination project number in the Project field (next to the Project link) and clicking the GO button. |
Fund Code |
Display Only |
A two-digit code representing a specific combination of federal, state, and “other” sources of funding. The relationship between the fund code and the Federal participation on the project is established via the Fund Description screen. |
Fund Code Description |
Display Only |
A description of the fund code. |
Federal % |
Display Only |
The percentage of Federal participation available under this FPN for the associated fund code. This value can range from ‘0.00’ to ‘100.00’. |
State % |
Display Only |
The percentage of State participation available under this FPN for the associated fund code. This value can range from ‘0.00’ to ‘100.00’. |
Other % |
Display Only |
The percentage of participation from “other” outside agencies for the associated fund code. This value can range from ‘0.00’ to ‘100.00’. Multiple agencies may be participating in the funding, but the percentage is displayed as an aggregate. In other words, if two other agencies are each providing 10% of the funding, the percentage listed in this field is 20%.
Note: If this is a municipal project, the municipality is only listed as an other agency if they are being reimbursed less than 100% of the construction costs for the project. |
Urban Area Indicator |
Display Only |
This field describes whether the area of the project funded by this FPN is located inside (I) or outside (O) of an urban area. |
Federal Project Number (FPN) |
Display Only |
The Federal Project Number (FPN) assigned to the project. Each FPN and its related data is entered on the Federal Estimate Construction Engineering Summary screen. |
Federal Project Status |
Display Only |
This field indicates whether the project requires federal oversight, and whether it is on or off the National Highway System (NHS). Valid values are:
- PENNDOT Oversight NHS
- PENNDOT Oversight Non-NHS
- Federal Oversight
- Non-Federal (100% State)
Note: Non-Federal, or 100% State projects are not included in the Federal Aid reports. However, a ‘state’ version of the reports exists. See "Tell Me About Non-Federal Aid Report by Fund Code" or "Tell Me About Non-Federal Aid Report by SPN" under "Project Funding" in the Help system. |
Federal Work Type |
Display Only |
The code identifying the type of work. The federal work type codes are maintained by FHWA. |
Federal Work Type Description |
Display Only |
A description of the federal work type. |
ALT |
Display Only |
The alternate code for the design item. This field is only displayed for the preliminary version of the report. Valid values are:
- Blank - Standalone item
- E - Either item (as-designed)
- O - Or item (alternate)
- A - And item
|
Item Number |
Display Only |
The number identifying the item linked to the FPN through the associated fund code. |
Item Type |
Display Only |
The type of construction item. This field is only displayed for the As-Built version of the report. Valid values are:
- Blank - Construction item
- A - Actual Force Account
- C - Contract Item
- D - Final Force Account Decrease
- E - Extra Work Item
- F - Estimated Force Account
- I - Final Force Account Increase
- L - Legal Claim Resolution
- P - Adjustment for Deficiencies
- X - Incentive Payment
|
Quantity |
Display Only |
The quantity of the item which is being funded by the FPN. This may be part or all of the item quantity. In the case of the As-Built report, the quantity reflects the current quantity net of any approved work orders. The report is available throughout the Construction phase of the project, so that this quantity may change up until the point the project is finalized. |
Unit of Measure |
Display Only |
The unit of measure for each item. |
Unit Price |
Display Only |
The price of one unit of the item. When the report is for the preliminary estimate, this is the estimated unit price from the design estimate. For the as-bid report, this is the bid price from the bid schedule of prices. For the as-built version of the report, this is the construction unit price. |
Item Total |
Display Only |
The cost of the quantity of the item that is associated with the FPN. This value is calculated by multiplying the Quantity * Unit Price.
Note: Because the total item quantity for the project may be greater than the item quantity associated with this fund code, the value in this column may not reflect the item total for the project as a whole. |
Item Description |
Display Only |
The description of the item appears under the item number. |
Item Total (for Fund Code) |
Display Only |
The total cost of all items associated with the fund code. This value is calculated by summing the item totals. |
Federal Funds Requested Total |
Display Only |
This is the total amount of Federal funds requested for the fund code. It is calculated by multiplying the Item Total for the fund code by the Federal Percentage. |
State and Other Funds Total |
Display Only |
This total represents the difference between the Item Total for the fund code and the Federal Funds Requested Total. |
Total Cost (without CENG) |
Display Only |
This is a calculated value representing the total costs associated with all fund codes whose federal work type is not designated as “CENG” (Construction Engineering Costs). |
Total Federal Funds Requested (without CENG) |
Display Only |
This is a calculated value representing the total costs associated with all fund codes whose federal work type is not designated as “CENG” multiplied by the federal percentage for each fund code.
If the value in the Federal % field is less than 100%, the cents appearing in the cost are truncated to zero as required by FHWA. |
Total State and Other Funds (without CENG) |
Display Only |
This is a calculated value representing the total costs associated with all fund codes whose federal work type is not designated as “CENG” minus the total federal funds requested whose federal work type is not designated as “CENG”. |
CENG - State Forces (SF) % |
Display Only |
This is the percentage of construction engineering costs associated with state forces. This value is used in combination with “CENG as % of Total” percentage to derive each of the CENG costs.
This value can range from ‘0.00’ to ‘100.00’. |
Total Cost CENG - SF % |
Display Only |
This is the total construction engineering costs associated with state forces. The formula used to calculate this field is:
Total Cost CENG - SF % = (CENG-SF % * CENG as % of Total * Total Cost w/o CENG) / 100 |
Federal Funds Requested CENG - SF % |
Display Only |
This is the portion of the total construction engineering costs associated with state forces that are funded by FHWA. The formula used to calculate this field is:
Federal Funds Requested CENG - SF % = (CENG-SF % * CENG as % of Total * Federal Funds Requested w/o CENG) / 100
If these costs exceed the calculated amount of the Total Costs CENG-SF column multiplied by the Federal percentage by $1.00 or less, $1.00 is subtracted from this subtotal. |
State and Other Funds CENG - SF % |
Display Only |
This is the portion of the total construction engineering costs associated with state forces that are funded by state and other sources. This number represents the difference between the Total Cost CENG-SF% and the Federal Funds Requested CENG-SF using the formula:
State and Other Funds CENG - SF % = Total Cost CENG-SF % - Federal Funds Requested CENG - SF |
CENG - Consultant Forces (CF) % |
Display Only |
This is the percentage of construction engineering costs associated with consultant forces. This value is used in combination with “CENG as % of Total” percentage to derive each of the CENG costs.
This value can range from ‘0.00’ to ‘100.00’. |
Total Cost CENG - CF % |
Display Only |
This is the total construction engineering costs associated with consultant forces. The formula used to calculate this field is:
Total Cost CENG - CF % = (CENG-CF % * CENG as % of Total * Total Cost w/o CENG) / 100 |
Federal Funds Requested CENG - CF % |
Display Only |
This is the portion of the total construction engineering costs associated with consultant forces that are funded by FHWA. The formula used to calculate this field is:
Federal Funds Requested CENG - CF % = (CENG-CF % * CENG as % of Total * Federal Funds Requested w/o CENG) / 100
If these costs exceed the calculated amount of the Total Costs CENG-CF column multiplied by the Federal percentage by $1.00 or less, $1.00 is subtracted from this subtotal. |
State and Other Funds CENG - CF % |
Display Only |
This is the portion of the total construction engineering costs associated with consultant forces that are funded by state and other sources. This number represents the difference between the Total Cost CENG-CF% and the Federal Funds Requested CENG-CF using the formula:
State and Other Funds CENG - CF % = Total Cost CENG-CF % - Federal Funds Requested CENG - CF |
CENG - Local Forces (LF) % |
Display Only |
This is the percentage of construction engineering associated with local forces. This value is used in combination with “CENG as % of Total” percentage to derive each of the CENG costs.
This value can range from ‘0.00’ to ‘100.00’. |
Total Cost CENG - LF % |
Display Only |
This is the total construction engineering costs associated with local forces. The formula used to calculate this field is:
Total Cost CENG - LF % = (CENG-LF % * CENG as % of Total * Total Cost w/o CENG) / 100 |
Federal Funds Requested CENG - LF % |
Display Only |
This is the portion of the total construction engineering costs associated with local forces that are funded by FHWA. The formula used to calculate this field is:
Federal Funds Requested CENG - LF % = (CENG-LF % * CENG as % of Total * Federal Funds Requested w/o CENG) / 100 |
State and Other Funds CENG - LF % |
Display Only |
This is the portion of the total construction engineering costs associated with local forces that are funded by state and other sources. This number represents the difference between the Total Cost CENG-LF% and the Federal Funds Requested CENG-LF using the formula:
State and Other Funds CENG - LF % = Total Cost CENG-LF % - Federal Funds Requested CENG - LF |
Grand Total - Total Cost |
Display Only |
This is the sum of the values in the Total Cost column. The exact number of cents displayed in the cost is always rounded so that it is always zero as required by FHWA. Rounding the largest of the state, consultant or local force Total Cost amounts does this. |
Grand Total - Federal Funds Requested |
Display Only |
This is the sum of the values in the Federal Funds Requested column. The exact number of cents displayed in the cost is always rounded so that it is always zero as required by FHWA. Rounding the largest of the state, consultant or local force Total Cost amounts does this. |
Grand Total - State and Other Funds |
Display Only |
This is the sum of the values in the State and Other Funds column. |