Justify Item Cost - Force Account Estimate

<H2 class=form>Description</H2>
<BLOCKQUOTE>This function allows users to create an item cost justification for a work order or workspace item based on the estimated cost of a force account. This includes a detailed breakdown of the equipment, labor, and material required to perform the work. Authorized users can access the Justify Item Cost - Force Account Estimate function by selecting "Force Account Estimate" from the Add links on the Work Order Item Justification or Workspace Item Cost Justification screen, then creating the three component estimates - Equipment Breakdown, Material Breakdown, and Labor Breakdown on separate screens.
<P><BR>Note: The titles of the screens include either "Work Order" or "Workspace", depending on where the screen was accessed. This Help document is written from the point of view of a work order. The steps for creating a force account estimate for the workspace item are identical. Where necessary, any minor differences have been highlighted in Notes.<BR></P></BLOCKQUOTE><BR>
<H2 class=form>Quick Navigation</H2>
<BLOCKQUOTE><FONT face=Helvetica size=2></FONT><FONT face=Arial size=2>The following table provides an overview of the steps in this process. Detailed step-by-step directions are provided in the next section.</FONT>
<TABLE border=1>
<TBODY>
<TR vAlign=top>
<TD width=199><B><FONT face=Arial size=2>From this screen…</FONT></B></TD>
<TD width=391><B><FONT face=Arial size=2>perform this action:</FONT></B></TD></TR>
<TR vAlign=top>
<TD width=199><FONT face=Arial size=2>Navigation bar</FONT></TD>
<TD width=391><FONT face=Arial size=2>Select Contractor Services</FONT>
<P><FONT face=Arial size=2>Select Estimates and Work Orders option</FONT>
<P><B><I><FONT face=Arial size=2>Note</FONT></I></B><I><FONT face=Arial size=2>: To navigate to the Workspace, use the My Projects option beneath Contractor Services. On the My Projects screen, select the project, then choose "Workspace" from the Go links and click the GO button.</FONT></I></P></TD></TR>
<TR vAlign=top>
<TD width=199><FONT face=Arial size=2>Estimates and Work Orders home page</FONT></TD>
<TD width=391><FONT face=Arial size=2>Choose "Work Orders by Status" as the Report type</FONT>
<P><FONT face=Arial size=2>Enter search criteria</FONT>
<P><FONT face=Arial size=2>Click SEARCH button</FONT></P></TD></TR>
<TR vAlign=top>
<TD width=199><FONT face=Arial size=2>Work Orders by Status list</FONT></TD>
<TD width=391><FONT face=Arial size=2>Click Work Order Number hyperlink</FONT></TD></TR>
<TR vAlign=top>
<TD width=199><FONT face=Arial size=2>Work Order screen</FONT></TD>
<TD width=391><FONT face=Arial size=2>Click Number hyperlink in the Number of Items field</FONT></TD></TR>
<TR vAlign=top>
<TD width=199><FONT face=Arial size=2>Work Order Items list</FONT></TD>
<TD width=391><FONT face=Arial size=2>Click Item Number hyperlink for the item requiring justification</FONT></TD></TR>
<TR vAlign=top>
<TD width=199><FONT face=Arial size=2>Work Order Item Detail screen</FONT></TD>
<TD width=391><FONT face=Arial size=2>Click Justification link</FONT></TD></TR>
<TR vAlign=top>
<TD width=199><FONT face=Arial size=2>Work Order Item Cost Justification screen</FONT></TD>
<TD width=391><FONT face=Arial size=2>Choose Justification method from drop-down list</FONT>
<P><FONT face=Arial size=2>Click the SAVE button</FONT>
<P><FONT face=Arial size=2>Select "Force Account" from the Add links and click the ADD button</FONT></P></TD></TR>
<TR vAlign=top>
<TD width=199><FONT face=Arial size=2>Force Account Estimate screen</FONT></TD>
<TD width=391><FONT face=Arial size=2>Choose "Material Cost Breakdown" from the Add links and click the ADD button</FONT></TD></TR>
<TR vAlign=top>
<TD width=199><FONT face=Arial size=2>Material Cost Breakdown</FONT></TD>
<TD width=391><FONT face=Arial size=2>Enter Material Description, Quantity and Unit Price</FONT>
<P><FONT face=Arial size=2>Click ADD button</FONT>
<P><FONT face=Arial size=2>Repeat as necessary</FONT>
<P><FONT face=Arial size=2>Click SAVE&amp;EXIT</FONT></P></TD></TR>
<TR vAlign=top>
<TD width=199><FONT face=Arial size=2>Force Account Estimate screen</FONT></TD>
<TD width=391><FONT face=Arial size=2>Choose "Labor Cost Breakdown" from the Add links and click the ADD button</FONT></TD></TR>
<TR vAlign=top>
<TD width=199><FONT face=Arial size=2>Labor Cost Breakdown screen</FONT></TD>
<TD width=391><FONT face=Arial size=2>Enter Labor Classification, Hours and Rate</FONT>
<P><FONT face=Arial size=2>Click ADD button</FONT>
<P><FONT face=Arial size=2>Repeat as necessary</FONT>
<P><FONT face=Arial size=2>Click SAVE&amp;EXIT</FONT></P></TD></TR>
<TR vAlign=top>
<TD width=199><FONT face=Arial size=2>Force Account Estimate screen</FONT></TD>
<TD width=391><FONT face=Arial size=2>Choose "Equipment Cost Breakdown" from the Add links and click the ADD button</FONT></TD></TR>
<TR vAlign=top>
<TD width=199><FONT face=Arial size=2>Equipment Cost Breakdown screen</FONT></TD>
<TD width=391><FONT face=Arial size=2>Enter Equipment Description, Hours and Rate</FONT>
<P><FONT face=Arial size=2>Click ADD button</FONT>
<P><FONT face=Arial size=2>Repeat as necessary</FONT>
<P><FONT face=Arial size=2>Click SAVE&amp;EXIT</FONT></P></TD></TR>
<TR vAlign=top>
<TD width=199><FONT face=Arial size=2>Force Account Estimate screen</FONT></TD>
<TD width=391><FONT face=Arial size=2>Enter Subcontractor Cost</FONT>
<P><FONT face=Arial size=2>Press TAB key</FONT>
<P><FONT face=Arial size=2>Enter Service by Others Costs</FONT>
<P><FONT face=Arial size=2>Press TAB key</FONT>
<P><FONT face=Arial size=2>Click SAVE&amp;EXIT</FONT></P></TD></TR></TBODY></TABLE><BR><FONT face=Helvetica size=2></FONT></BLOCKQUOTE><BR>
<H2 class=form>Step-by-Step Directions</H2>
<BLOCKQUOTE>
<P>
<TABLE border=1>
<TBODY>
<TR vAlign=top>
<TD width=151><B><FONT face=Arial size=2>User Action</FONT></B></TD>
<TD width=439><B><FONT face=Arial size=2>Result</FONT></B></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Open your browser software and access the ECMS Welcome page.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The ECMS Welcome page is displayed with the navigation bar on the left.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Using the Registered Users Login fields at the top of the navigation bar, enter your user ID and password. Click GO or tap the Enter key.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The ECMS Welcome page appears. Your user name now appears at the top of the navigation bar, and the navigation bar options are tailored to your security group(s).</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>From the navigation bar, select the Contractor Services option. </FONT></TD>
<TD width=439><FONT face=Arial size=2>The Contractor Services option available to your user group are displayed.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Select the Estimates and Work Orders option beneath Contractor Services on the navigation bar.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The Estimates and Work Orders home page is displayed.</FONT>
<P><B><I><FONT face=Arial size=2>Note</FONT></I></B><I><FONT face=Arial size=2>: To navigate to the Workspace, use the My Projects option beneath Contractor Services. On the My Projects screen, select the project, then choose "Workspace" from the Go links and click the GO button.</FONT></I><FONT face=Arial size=2> </FONT><I><FONT face=Arial size=2>From the Workspace screen, click the Item Number hyperlink to navigate to the Workspace Item detail screen, then click the Justification link.</FONT></I></P></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Select “Work Orders by Status” from the Report field.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The entry you selected appears in the field.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>If desired, enter additional search criteria, such as project number or work order status to narrow the search. </FONT></TD>
<TD width=439><FONT face=Arial size=2>The criteria you entered appear in the fields.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Click the SEARCH button.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The Work Orders by Status list is displayed and includes work orders matching the search criteria you entered.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Click the Work Order Number hyperlink.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The Work Order screen for the selected work order is displayed.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Click the Number hyperlink in the Number of Items field.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The Work Order Items list is displayed.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Click the Item Number hyperlink for the item whose cost you wish to justify.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The Work Order Item detail screen is displayed.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Click the Justification hyperlink.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The Work Order Item Cost Justification screen is displayed.</FONT>
<P><B><I><FONT face=Arial size=2>Note</FONT></I></B><I><FONT face=Arial size=2>: For Workspace items, the screen title changes to "Workspace Item Cost Justification".</FONT></I></P></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Select the Justification Method from the drop-down list.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The method you selected appears in the field.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Select Force Account Estimate" from the Add links and click the ADD button.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The Force Account Estimate screen is displayed.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><IMG height=1 alt="" src="/icons/ecblank.gif" width=1 border=0></TD>
<TD width=439>
<DIV align=center><B><I><FONT face=Arial size=2>*****Create Material Cost Breakdown*****</FONT></I></B></DIV></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Select "Material Cost Breakdown" from the Add links and click the ADD button.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The Material Breakdown screen is displayed.</FONT>
<P><B><I><FONT face=Arial size=2>Note</FONT></I></B><I><FONT face=Arial size=2>: The breakdown screen titles change based on whether this is a work order item or a workspace item. For example, when accessed via a work order item, this screen title will be "Work Order Material Breakdown".</FONT></I></P></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Enter a description of the material in the Description field.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The text you entered appears in the field.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Enter the quantity of the material in the Quantity field.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The value you entered appears in the field.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Enter the unit price in the Unit Price field.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The value you entered appears in the field.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Click the ADD button under the Amount column.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The system calculates the total for the material by multiplying the quantity and unit price. The result is displayed under the Amount column, and a new line for data entry appears below it.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>If desired, continue to add material descriptions, quantities and unit prices, clicking the ADD button after each entry.</FONT></TD>
<TD width=439><FONT face=Arial size=2>As you add the material information, the system sums the amount, calculates the dollar amount of the sales tax, multiplies it by the material amount, and displays the subtotal. The system then multiplies the subtotal by the overhead and displays the total at the bottom of the screen.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>When you are finished entering the material breakdown, click the SAVE&amp;EXIT button.</FONT></TD>
<TD width=439><FONT face=Arial size=2>A 'please wait' message is displayed. When processing is complete, a 'successful' message is displayed.</FONT>
<P><B><I><FONT face=Arial size=2>Note</FONT></I></B><I><FONT face=Arial size=2>: To change a line in the material breakdown, you must delete then re-add it. Select the line using the checkbox to the left of it, then click the SAVE button to delete it.</FONT></I></P></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Click OK on the message box.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The message box closes, and you are returned to the Force Account Estimate screen. A link to the material breakdown you just created appears in the Total Material Cost field.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Click the EDIT button.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The screen switches to edit mode.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><IMG height=1 alt="" src="/icons/ecblank.gif" width=1 border=0></TD>
<TD width=439>
<DIV align=center><B><I><FONT face=Arial size=2>*****Create Labor Cost Breakdown*****</FONT></I></B></DIV></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Select Labor Cost Breakdown from the Add links and click the ADD button.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The Labor Breakdown screen is displayed. This screen performs the same function as the Material Breakdown but for the labor portion of the force account estimate.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Enter the name of the labor classification in the Classification field.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The title you entered appears in the field.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Enter the estimated number of hours required for this classification in the Hours field.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The value you entered appears in the field.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Enter the hourly rate in the Rate/Hr field.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The value you entered appears in the field.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Click the ADD button under the Amount column.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The system calculates the total for the labor by multiplying the number of hours by the rate per hour. The result is displayed under the Amount column, and a new line for data entry appears below it.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>If desired, continue to add labor classifications, hours and rates, clicking the ADD button after each entry.</FONT></TD>
<TD width=439><FONT face=Arial size=2>As you add the labor information, the system sums the amounts, calculates the dollar amount of the insurance/taxes percentage (defaults to 10%), multiplies it by the labor amount, and displays the subtotal. The system then multiplies the subtotal by the overhead and displays the total at the bottom of the screen.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>When you are finished entering the labor breakdown, click the SAVE&amp;EXIT button.</FONT></TD>
<TD width=439><FONT face=Arial size=2>A 'please wait' message is displayed. When processing is complete, a 'successful' message is displayed.</FONT>
<P><B><I><FONT face=Arial size=2>Note</FONT></I></B><I><FONT face=Arial size=2>: To change a line in the labor breakdown, you must delete then re-add it. Select the line using the checkbox to the left of it, then click the SAVE button to delete it.</FONT></I></P></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Click OK on the message box.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The message box closes, and you are returned to the Force Account Estimate screen. A link to the labor breakdown you just created appears in the Total Labor Cost field.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Click the EDIT button.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The screen switches to edit mode.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><IMG height=1 alt="" src="/icons/ecblank.gif" width=1 border=0></TD>
<TD width=439>
<DIV align=center><B><I><FONT face=Arial size=2>*****Create Equipment Cost Breakdown*****</FONT></I></B></DIV></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Select "Equipment Cost Breakdown" from the Add links and click the ADD button.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The Equipment Breakdown screen is displayed. This screen performs the same function as the Material and Labor Breakdown screens but for the equipment portion of the force account estimate.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Enter a description of the equipment in the Equipment Description field.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The description you entered appears in the field.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Enter the estimated number of hours required for this equipment in the Hours field.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The value you entered appears in the field. </FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Enter the hourly rate in the Rate/Hr field.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The value you entered appears in the field. (The hourly rate includes estimated operating costs).</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Click the ADD button under the Amount column.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The system calculates the total for the equipment by multiplying the number of hours by the rate per hour. The result is displayed under the Amount column, and a new line for data entry appears below it.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>If desired, continue to add equipment descriptions, hours and rates, clicking the ADD button after each entry.</FONT></TD>
<TD width=439><FONT face=Arial size=2>As you add the equipment information, the system sums the amounts, calculates the dollar amount of the overhead and displays the total at the bottom of the screen.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>When you are finished entering the equipment breakdown, click the SAVE&amp;EXIT button.</FONT></TD>
<TD width=439><FONT face=Arial size=2>A 'please wait' message is displayed. When processing is complete, a 'successful' message is displayed.</FONT>
<P><B><I><FONT face=Arial size=2>Note</FONT></I></B><I><FONT face=Arial size=2>: To change a line in the equipment breakdown, you must delete then re-add it. Select the line using the checkbox to the left of it, then click the SAVE button to delete it.</FONT></I></P></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Click OK on the message box.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The message box closes, and you are returned to the Force Account Estimate screen. A link to the labor breakdown you just created appears in the Total Labor Cost field.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Click the EDIT button.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The screen switches to edit mode.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><IMG height=1 alt="" src="/icons/ecblank.gif" width=1 border=0></TD>
<TD width=439>
<DIV align=center><B><I><FONT face=Arial size=2>*****Complete Force Account Estimate Fields*****</FONT></I></B></DIV></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>If applicable, enter the estimated subcontract cost in the Subcontractor Cost field, then use the Tab key to move to the Service Costs by Others field.</FONT></TD>
<TD width=439><FONT face=Arial size=2>As you tab to the next field, the system automatically calculates the dollar amount of the Subcontractor Overhead, and adds it, along with the base subcontractor cost to the Grand total.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>If applicable, enter the estimated costs of services in the Service Costs by Others field, then click the Tab key.</FONT></TD>
<TD width=439><FONT face=Arial size=2>As you tab to the next field, the system automatically calculates the dollar amount of the SBO Overhead, and adds it, along with the base SBO cost to the Grand total.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Click the SAVE&amp;EXIT button.</FONT></TD>
<TD width=439><FONT face=Arial size=2>A 'please wait' message is displayed. When processing is complete, a 'successful' message is displayed.</FONT></TD></TR>
<TR vAlign=top>
<TD width=151><FONT face=Arial size=2>Click OK on the message box.</FONT></TD>
<TD width=439><FONT face=Arial size=2>The message box closes, and you are returned to the Work Order (or Workspace) Item Cost Justification screen. A link to the Force Account Estimate appears in the Force Account Estimate field.</FONT></TD></TR></TBODY></TABLE></P></BLOCKQUOTE>

Description

This function allows users to create an item cost justification for a work order or workspace item based on the estimated cost of a force account. This includes a detailed breakdown of the equipment, labor, and material required to perform the work. Authorized users can access the Justify Item Cost - Force Account Estimate function by selecting "Force Account Estimate" from the Add links on the Work Order Item Justification or Workspace Item Cost Justification screen, then creating the three component estimates - Equipment Breakdown, Material Breakdown, and Labor Breakdown on separate screens.


Note: The titles of the screens include either "Work Order" or "Workspace", depending on where the screen was accessed. This Help document is written from the point of view of a work order. The steps for creating a force account estimate for the workspace item are identical. Where necessary, any minor differences have been highlighted in Notes.


Quick Navigation

The following table provides an overview of the steps in this process. Detailed step-by-step directions are provided in the next section.
From this screen… perform this action:
Navigation bar Select Contractor Services

Select Estimates and Work Orders option

Note: To navigate to the Workspace, use the My Projects option beneath Contractor Services. On the My Projects screen, select the project, then choose "Workspace" from the Go links and click the GO button.

Estimates and Work Orders home page Choose "Work Orders by Status" as the Report type

Enter search criteria

Click SEARCH button

Work Orders by Status list Click Work Order Number hyperlink
Work Order screen Click Number hyperlink in the Number of Items field
Work Order Items list Click Item Number hyperlink for the item requiring justification
Work Order Item Detail screen Click Justification link
Work Order Item Cost Justification screen Choose Justification method from drop-down list

Click the SAVE button

Select "Force Account" from the Add links and click the ADD button

Force Account Estimate screen Choose "Material Cost Breakdown" from the Add links and click the ADD button
Material Cost Breakdown Enter Material Description, Quantity and Unit Price

Click ADD button

Repeat as necessary

Click SAVE&EXIT

Force Account Estimate screen Choose "Labor Cost Breakdown" from the Add links and click the ADD button
Labor Cost Breakdown screen Enter Labor Classification, Hours and Rate

Click ADD button

Repeat as necessary

Click SAVE&EXIT

Force Account Estimate screen Choose "Equipment Cost Breakdown" from the Add links and click the ADD button
Equipment Cost Breakdown screen Enter Equipment Description, Hours and Rate

Click ADD button

Repeat as necessary

Click SAVE&EXIT

Force Account Estimate screen Enter Subcontractor Cost

Press TAB key

Enter Service by Others Costs

Press TAB key

Click SAVE&EXIT



Step-by-Step Directions

User Action Result
Open your browser software and access the ECMS Welcome page. The ECMS Welcome page is displayed with the navigation bar on the left.
Using the Registered Users Login fields at the top of the navigation bar, enter your user ID and password. Click GO or tap the Enter key. The ECMS Welcome page appears. Your user name now appears at the top of the navigation bar, and the navigation bar options are tailored to your security group(s).
From the navigation bar, select the Contractor Services option. The Contractor Services option available to your user group are displayed.
Select the Estimates and Work Orders option beneath Contractor Services on the navigation bar. The Estimates and Work Orders home page is displayed.

Note: To navigate to the Workspace, use the My Projects option beneath Contractor Services. On the My Projects screen, select the project, then choose "Workspace" from the Go links and click the GO button. From the Workspace screen, click the Item Number hyperlink to navigate to the Workspace Item detail screen, then click the Justification link.

Select “Work Orders by Status” from the Report field. The entry you selected appears in the field.
If desired, enter additional search criteria, such as project number or work order status to narrow the search. The criteria you entered appear in the fields.
Click the SEARCH button. The Work Orders by Status list is displayed and includes work orders matching the search criteria you entered.
Click the Work Order Number hyperlink. The Work Order screen for the selected work order is displayed.
Click the Number hyperlink in the Number of Items field. The Work Order Items list is displayed.
Click the Item Number hyperlink for the item whose cost you wish to justify. The Work Order Item detail screen is displayed.
Click the Justification hyperlink. The Work Order Item Cost Justification screen is displayed.

Note: For Workspace items, the screen title changes to "Workspace Item Cost Justification".

Select the Justification Method from the drop-down list. The method you selected appears in the field.
Select Force Account Estimate" from the Add links and click the ADD button. The Force Account Estimate screen is displayed.
*****Create Material Cost Breakdown*****
Select "Material Cost Breakdown" from the Add links and click the ADD button. The Material Breakdown screen is displayed.

Note: The breakdown screen titles change based on whether this is a work order item or a workspace item. For example, when accessed via a work order item, this screen title will be "Work Order Material Breakdown".

Enter a description of the material in the Description field. The text you entered appears in the field.
Enter the quantity of the material in the Quantity field. The value you entered appears in the field.
Enter the unit price in the Unit Price field. The value you entered appears in the field.
Click the ADD button under the Amount column. The system calculates the total for the material by multiplying the quantity and unit price. The result is displayed under the Amount column, and a new line for data entry appears below it.
If desired, continue to add material descriptions, quantities and unit prices, clicking the ADD button after each entry. As you add the material information, the system sums the amount, calculates the dollar amount of the sales tax, multiplies it by the material amount, and displays the subtotal. The system then multiplies the subtotal by the overhead and displays the total at the bottom of the screen.
When you are finished entering the material breakdown, click the SAVE&EXIT button. A 'please wait' message is displayed. When processing is complete, a 'successful' message is displayed.

Note: To change a line in the material breakdown, you must delete then re-add it. Select the line using the checkbox to the left of it, then click the SAVE button to delete it.

Click OK on the message box. The message box closes, and you are returned to the Force Account Estimate screen. A link to the material breakdown you just created appears in the Total Material Cost field.
Click the EDIT button. The screen switches to edit mode.
*****Create Labor Cost Breakdown*****
Select Labor Cost Breakdown from the Add links and click the ADD button. The Labor Breakdown screen is displayed. This screen performs the same function as the Material Breakdown but for the labor portion of the force account estimate.
Enter the name of the labor classification in the Classification field. The title you entered appears in the field.
Enter the estimated number of hours required for this classification in the Hours field. The value you entered appears in the field.
Enter the hourly rate in the Rate/Hr field. The value you entered appears in the field.
Click the ADD button under the Amount column. The system calculates the total for the labor by multiplying the number of hours by the rate per hour. The result is displayed under the Amount column, and a new line for data entry appears below it.
If desired, continue to add labor classifications, hours and rates, clicking the ADD button after each entry. As you add the labor information, the system sums the amounts, calculates the dollar amount of the insurance/taxes percentage (defaults to 10%), multiplies it by the labor amount, and displays the subtotal. The system then multiplies the subtotal by the overhead and displays the total at the bottom of the screen.
When you are finished entering the labor breakdown, click the SAVE&EXIT button. A 'please wait' message is displayed. When processing is complete, a 'successful' message is displayed.

Note: To change a line in the labor breakdown, you must delete then re-add it. Select the line using the checkbox to the left of it, then click the SAVE button to delete it.

Click OK on the message box. The message box closes, and you are returned to the Force Account Estimate screen. A link to the labor breakdown you just created appears in the Total Labor Cost field.
Click the EDIT button. The screen switches to edit mode.
*****Create Equipment Cost Breakdown*****
Select "Equipment Cost Breakdown" from the Add links and click the ADD button. The Equipment Breakdown screen is displayed. This screen performs the same function as the Material and Labor Breakdown screens but for the equipment portion of the force account estimate.
Enter a description of the equipment in the Equipment Description field. The description you entered appears in the field.
Enter the estimated number of hours required for this equipment in the Hours field. The value you entered appears in the field.
Enter the hourly rate in the Rate/Hr field. The value you entered appears in the field. (The hourly rate includes estimated operating costs).
Click the ADD button under the Amount column. The system calculates the total for the equipment by multiplying the number of hours by the rate per hour. The result is displayed under the Amount column, and a new line for data entry appears below it.
If desired, continue to add equipment descriptions, hours and rates, clicking the ADD button after each entry. As you add the equipment information, the system sums the amounts, calculates the dollar amount of the overhead and displays the total at the bottom of the screen.
When you are finished entering the equipment breakdown, click the SAVE&EXIT button. A 'please wait' message is displayed. When processing is complete, a 'successful' message is displayed.

Note: To change a line in the equipment breakdown, you must delete then re-add it. Select the line using the checkbox to the left of it, then click the SAVE button to delete it.

Click OK on the message box. The message box closes, and you are returned to the Force Account Estimate screen. A link to the labor breakdown you just created appears in the Total Labor Cost field.
Click the EDIT button. The screen switches to edit mode.
*****Complete Force Account Estimate Fields*****
If applicable, enter the estimated subcontract cost in the Subcontractor Cost field, then use the Tab key to move to the Service Costs by Others field. As you tab to the next field, the system automatically calculates the dollar amount of the Subcontractor Overhead, and adds it, along with the base subcontractor cost to the Grand total.
If applicable, enter the estimated costs of services in the Service Costs by Others field, then click the Tab key. As you tab to the next field, the system automatically calculates the dollar amount of the SBO Overhead, and adds it, along with the base SBO cost to the Grand total.
Click the SAVE&EXIT button. A 'please wait' message is displayed. When processing is complete, a 'successful' message is displayed.
Click OK on the message box. The message box closes, and you are returned to the Work Order (or Workspace) Item Cost Justification screen. A link to the Force Account Estimate appears in the Force Account Estimate field.