User Action |
Result |
If desired, enter a user-defined title for the checklist item in the Title field. |
This title will appear on the main Project Development Checklist screen separated from the standard title by a dash. For example, "Coordination Meetings - User Defined Title". |
Under the Environmental Clearances category of the Project Development Checklist, click the "Categorical Exclusion Evaluation - CEE" hyperlink. |
The checklist detail screen appears. |
Select the CEE Level from the drop-down list. |
The entry you selected appears in the field. Valid values are:
- Level 1A
- Level 1B
- Level 2
|
Enter the item numbers from the CEE in the Item Numbers field. |
The item numbers you entered appear in the field. |
If applicable, enter the Approved by FHWA date in mm/dd/yyyy format, or select the date using the Calendar/clock icon. |
The date you entered or selected appears in the field.
Note: This field is required when the CEE Level is 2.
|
Enter the approval date in mm/dd/yyyy format, or select the date using the Calendar/clock icon. |
The date you entered or selected appears in the field. |
Enter the name of the approver in the Approved By field. |
The name you entered appears in the field. |
If desired, enter text in the Comments field. |
The text you entered appears in the field. |
If desired, attach an EDMS document to the checklist item by clicking the SEL EDMS button. |
See "How Do I Attach an EDMS Document" for details. |
By default, the "Include in Bid Package" indicator is set to No and cannot be edited. |
This is a noncontractual checklist item. |
If the checklist item is complete, choose 'Yes' from the Completed radio button group. |
The selected radio button appears with a darkened center.
Note: This indicator has no effect on system processing. However, checklist items that are marked as completed appear with the 'completed' checkmark icon on the Project Development Checklist screen. Execute rules flags an error for each checklist item that is not marked as complete when the bid package is submitted or published.
|
When you are finished entering date, click the SAVE & EXIT button to save the checklist item and return to the Project Development Checklist screen. |
The checklist item is saved, and the Project Development Checklist screen is displayed. |