| User Action |
Result |
| Enter the percentage to be used in calculating the profit in the Profit Factor field. |
The value must be entered as v999. For example, if the profit factor is 4 percent, etner '.450'. |
| Choose Field or Office in the Overhead field to indicate which overhead rate applies to the task. |
The radio button you selected apprears with a darkened center.
Note: This field is hidden if the method of payment is Cost Per Unit or Specific Rate.
|
| Click SAVE COST FACTOR |
A message is displayed indicating the Cost Factor was successfully saved. |
| Click OK on the message box |
The message box closes and you are returned to the Cost Factors screen. |
| Enter a name for the escalation to be used in the Escalation Name field. |
The name you entered appears in the field.
Note: The name must be unique within this Part. For example, Part 1 cannot have two different escalations both named 'FY2003'.
|
| Enter the percentage to be used for the escalation calculation in the Escalation % field. |
The value must be entered as 999v99. For example, enter 5 percent as '005.000'. |
| Enter a brief description of how the escalation was calculated in the Escalation Calculation field. |
The description you entered appears in the field. |
| Click SAVE ESCALATION |
A message appears indicating the Escalation was successfully saved. |
| Click OK on the message box |
The message box closes and you are returned to the Cost Factors tab. |